Entergy New Orleans is committed to providing reliable service to our customers by investing in transmission projects that help strengthen the electric grid and reduce the risk of outages. Recent efforts in Mid-City, Gentilly, and New Orleans East reflect that commitment with crews completing major upgrades to our transmission and distribution lines.
To accomplish this, Entergy New Orleans deployed a highly specialized bare-hand crew to complete the work—an elite team of linemen trained to safely repair high-voltage, energized transmission lines. Keeping the lines energized during upgrades prevents power outages and ensures substations continue operating under normal, stable conditions.
The team recently completed work on a major transmission line in New Orleans, replacing older insulators on 26 towers with stronger, more modern equipment. Working in coordination with distribution and vegetation management teams, they also replaced aging wooden cross arms and cleared overgrown vegetation. This collaborative approach enhances both transmission and distribution reliability across the New Orleans service area.
Additional work is underway in New Orleans East, where the bare-hand crew is replacing insulators on several water-crossing circuits. The crew is scheduled to complete critical upgrades on the Michoud–Front transmission line crossing over Lake Pontchartrain. This line provides a vital interconnection between Entergy and Cleco and serves as an emergency power source for the New Orleans grid. These enhancements will significantly strengthen the electrical grid and improve regional reliability.
“These types of upgrades help prevent potential issues and keep the power flowing safely,” said Kenyon Stipe, transmission line supervisor at Entergy New Orleans. “Upgrading our equipment reduces the chance of outages and helps ensure reliable service for our customers.”
This work would not be possible without the expertise and collaboration of key personnel and partners. North Houston Pole Line provided experienced contract support. Linh Tran, Grid Engineer; Josh Rollins, Transmission OC; Kenyon Stipe Sr., Transmission Line Supervisor; and Frank Morse, Senior Manager of Transmission Lines, all played vital roles in planning and execution. The Tulane Network also contributed valuable support to the project’s success.
By completing this work with energized lines and minimizing disruption, Entergy New Orleans continues to meet its promise of delivering safe, reliable power to its customers.